My motions to a meeting of the carrigaline municipal district, 15-06-2020

1. That Ballygarvan village would be included as one of the recommended locations for installation of vehicle-activated speed signage. Ballygarvan has been identified by the Gardai as being a location that would benefit from such digital speed signage.

The response from the Area Engineer was that although she has planned to undertake speed surveys in a number of towns and villages around the Municipal District and to install vehicle-activated speed signage on the advice of the findings, if the Gardaí have already made a recommendation for such signage in a location, she would consider fast-tracking its installation in that location. I am to send on the correspondence from the Gardaí.  

2. That updates would be provided on the following ongoing key projects in our Municipal District:
a. Carrigaline Transportation and Public Realm Enhancement Plan
b. Glenbrook – Carrigaline/Ringaskiddy Greenway 
c. Ringaskiddy Public Realm Enhancement Plan
d. Ringaskiddy Village Enhancement Funding for Gobby Beach

The written response from the Municipal District Officer was as follows:

a. The procurement process for the TPREP is nearing a conclusion and the appointment of a Consultant is imminent. Consultation with Members and other stakeholders will be an important element of the plan preparation and we will be in a position to advise of associated timelines once the Consultant has been appointed. The Public Realm team were engaged during the preparation of the consultancy brief – and will be important stakeholders in the process – so both projects are aligned.

b. Traffic and Transportation Section is hoping to issue consultancy brief in Quarter 3 of 2020.

c and d. Carrigaline MD office is working with the Architects Department to progress a design to inform a phased approach to the overall public realm design for Ringaskiddy. COVID-19 has had an impact on the progress of these plans. Plans will be shared with the community association and with members once progressed in advance of a Part 8 Planning Application. Gobby Beach will form part of these plans and the balance of funding previously allocated under the Village Enhancement Fund remains available.

3. That Cork County Council would cut the grass verges on the L6518 from Moog to Ringaskiddy National School and on the R613 from Barnahely Cemetery to the junction with the N28.

The Area Engineer said that she would follow up on why the cutting did not take place on the cemetery to N28 section of the R613. Due to budgetary constraints, she said it was not the Area Office’s intention to cut road verges insofar as possible and so it was unlikely that the L6518 would be done.